| 
         JWA (John Wayne Airport): One of Those Defining 
        Moments 
         January 20, 2009  
        
        CALIFORNIA — John Wayne Airport (JWA), 
        a prominent, Los Angeles regional facility which is tightly surrounded 
        by high density commercial and residential areas and perched at the edge 
        of the Pacific Ocean, recently completed reconstruction of its primary 
        runway. Kimley Horn & Associates, Inc. provided project administration 
        and engineering while Butier Engineering, Inc. provided construction 
        management. The contractor, All American Asphalt, Inc., provided 
        construction supervision, materials, labor and equipment for the 
        building of the project 
        Primary work 
        included coring the top three inches of aged pavement on the 5,700 foot 
        main runway then re-paving the area with a PG 76-10 overlay.  
        Included in the specification was the requirement for protecting 68,000 
        square yards of runway shoulder and aprons with a protective coating 
        which was: 
        
        
          
             1. Waterborne 
            
        2. Environmentally clean (no VOC's, no HAP's, no toxins or  
                 
        carcinogens and no PAH's) 
             3. Fuel resistant 
             4. 'Skid neutral' 
        or better 
             5. Insoluble to 
        rain within 1 hour of curing 
             6. Able to cure at 
        night @ 50°F in less than six hours 
        
          
           Those requirements set standards 
          that only new innovation could  
          
           solve, no product currently 
          existed that would meet these  
          
           guidelines.  
          Due to its 
          neighborhood proximity the Airport is regularly closed between the 
          hours of 11:00 p.m. and 6:00 a.m. This presented the challenge of 
          developing and installing a coating that could be placed and would 
          achieve full cure within this time window so heavy jet traffic could, 
          uninterrupted, perform all normal activities.  Since the contract 
          penalty for interrupting normal JWA activities was $10,000 per 
          minute, the decision process for selecting a coating which met all 
          the requirements, especially those of the curing window was, to say 
          the least, characterized by heightened drama. 
          Ramsey Oil, 
          Inc. a division of All American Asphalt, Inc. would install the 
          coating.  Paul Snow, Ramsey’s crew manager, was tasked with 
          coordinating night time field test applications of coating 
          alternatives; which were then evaluated by JWA representatives.  After 
          considering many options provided through the All American management 
          team the head of procurement, John Todorovich, concurred with the JWA 
          representatives that the product supplied by Ecostar Science & 
          Technology, Inc. (a Lockheed Martin, Corp. spin-off) was the best 
          choice.  That product was Carbon Plex H-25; manufactured under an 
          Ecostar license by Delta Trading, Inc. of Bakersfield, CA.  
          The 
          installation of the coating was scheduled for late December 2008 but 
          40° 
          F night time temperatures left little margin for error, i.e. the 
          Carbon Plex emulsion, which has exhibited the quality of fully curing 
          down to that temperature, had only been tested at John Wayne at night 
          time with 50°F 
          temperatures.  The job was pushed to after the holidays with a “GO” 
          set for the evenings of January 8th and 9th.   
          Everyone was ‘antsy’ to wrap up this project after the months of 
          coating study; even if it meant going in the middle of the winter, at 
          night.  The weather report for those dates was for rising temperatures 
          and clear skies, with possible ‘Santa Anna’ winds which would provide 
          excellent drying conditions.  Everyone felt comfortable with pulling 
          off this last critical phase of the Project.  
        Seven thousand gallons of the 
        “Cold Cure” version of the Carbon Plex H-25 was prepared, then diluted 
        25% and shipped to the job site; ready to use.  A light tower rigged, 
        2,000 gallon Bearcat distributor truck was readied, together with three 
        mobile light tower platforms.  Against the back drop of jet engine roar 
        the Ramsey Oil crew put on their ‘game face’ and huddled in the staging 
        area at the pre-installation tailgate meeting with four JWA engineers 
        and two inspectors.  Air and pavement temperatures were in the low 50's 
        F.  The table was set for finishing the project except for one ‘fly in 
        the ointment’ - FOG.  Wet fog was peppering the faces of all the men; 
        and there was not a flutter of a breeze to move it.  The big question 
        was, “Should we scrub the mission or push on?”  Paul Snow, who had the 
        most experience with the Carbon Plex felt a cautious start was possible; 
        paying close attention to the ‘break’ time.  The plan was to install a 
        short run of the H-25, time the cure and then decide whether to ‘step on 
        the gas’ or scrub the effort for the night.  Tension was high with 
        everyone’s blood pressure ramping up.  The JWA engineers and inspectors 
        then present, huddled to consider the cautious start proposal, then 
        concurred with the All American crew manager; but their trepidation 
        could be summed up with one unnamed individual stating that “If this 
        application goes sideways you are going to see me hanging from the top 
        of that (nearby) 100 foot eucalyptus tree.” 
         At 10:45 p.m. 
        the gates were opened and the convoy of trucks was escorted out through 
        the fog hovering over the main runway. 
        
         As 
        the Carbon Plex H-25 does not need to be heated to cure under night time 
        conditions, minimal heat (110° 
        F) was used to encourage drying.  At 11:07 p.m. the first twelve foot 
        swath began at 0.10-0.12 gal/sq yd spread rate.  When the Bearcat 
        operator ‘dropped the hammer’ and disappeared into the fog on its first 
        mile plus run every eye at the start line leaned forward under the glare 
        of the light tower to glean information from the flow pattern and color 
        change of the freshly placed coating. 
        The entire span 
        of runway pavement surface had been saw cut with three eights inch deep 
        grooves at one inch on center.  A special characteristic of the Carbon 
        Plex H-25 is its rapid 10:1 (static/shear thin) viscosity rise after 
        being pumped and sprayed.  In less than one second from hitting the 
        pavement the static viscosity is nearly restored; assuring a significant 
        resistance to puddling in the grooves.  On this foggy night it was 
        performing as designed, with virtually no uneven film thickness between 
        the pavement surface and the groove bottoms.   
         At this point 
        other good things began to happen. Before the Bearcat returned painting 
        its second twelve foot swath, a black hue began to show in the over 
        spray zone.  The Carbon Plex emulsion was breaking!!  Even with the 
        atmospheric vapor content above the surface being at or near saturation 
        the exothermic reaction designed into the “Cold Cure” version of H-25 
        was kicking in and forcing the micronized emulsion water component to 
        volatize.  By the time the distributor truck returned a collective 
        “whew” had begun to set in.  The blood pressures of about two dozen hard 
        working men were rapidly falling.  Mental resignation letters were being 
        shredded. The JWA engineers granted that the installation could proceed. 
        By 1:45 a.m. the entire 640,000 s.f. was coated and curing at a 
        predictable pace.  At about 3:30 a.m. the entire job was drivable; even 
        though the fog had actually worsened at times.  No champagne was opened 
        but everyone associated with the effort felt as though it may have been 
        appropriate; as the first 
        critical stage of the job had been accomplished. 
        
          
        There are three 
        distinct stages to the life cycle of this type of pavement 
        preservation.   
         Stage 
        One had achieved complete 
        success.  The coating was installed and cured in the allotted time and 
        under the conditions prescribed.  Curing had progressed to a film 
        sufficiently tough to resist tire displacement as well as becoming water 
        fast with no chance of re-emulsification.   
         Stage 
        Two came the next morning 
        when all the ‘normal’ people who have jobs which allow them to stay at 
        home at night, could come out and witness the heavy jets trafficking 
        over the fresh, shiny black coating.  Most importantly, like some clean 
        room entry mat, the jets then would roll over the three foot wide, white 
        thermoplastic stripe defining the runway, without one hint of any 
        tracking!!  “Yeah team” could be read on the face of each early morning 
        inspector as they knew ‘they’ had made the right decision(s). The 
        performance was analogous to the test sites which, incidentally, were 
        done without the benefit of fog.   
         Stage 
        Three will be to watch the 
        product perform over the coming months and years; to see how well it 
        endures under the insult of hot jet exhaust, unspent J5 vapor, salty fog 
        and a hot Southern California solar bake. 
         While the 
        immediate reward is “No Penalties” there is also an intangible 
        yield to this type of project.  That yield is the feeling of deep 
        satisfaction within every professional associated with this effort; of 
        thoughtfully and vigorously pushing the envelope and succeeding to 
        achieve against unusual challenges.  We are also relieved to report that 
        the next morning’s sun brightly shone on the 100 foot tall eucalyptus 
        revealing no more weight in its branches than it bore the previous day!
         
        
        William Coe 
        
        President, Ecostar Science and 
        Technology, Inc. 
          
        
        One of Those Defining Moments
         
        
        There are instances when years of research and hard work  
        
        showcase innovations that will leave a large footprint,  
        
        moments that define a new era. 
        
        
          
          
           |